The U.S. Navy accepted delivery of the USS Little Rock (LCS 9) during a ceremony Monday at Fincantieri Marinette Marine (FMM) shipyard in Marinette, Wis.

The Little Rock is the 11th littoral combat ship (LCS) to be delivered to the Navy and the fifth Freedom-class variant to join the fleet. The delivery marks the official transfer of the ship from the shipbuilder, part of a Lockheed Martin-led team, to the Navy. It is the final milestone prior to commissioning, which is planned for December in Buffalo, N.Y.

"Today marks a significant milestone in the life of the future USS Little Rock, an exceptional ship which will conduct operations around the globe," said Capt. Mike Taylor, LCS program manager. "I look forward to seeing Little Rock join her sisterships this fall, with 100 percent of propulsion power available for unrestricted use."

Capt. Shawn Johnston, commander, LCS Squadron Two (COMLCSRON TWO), welcomed Little Rock to the fleet.

"Successful completion of this milestone is another important step to bring more LCSes to the fleet," Johnston said. "We look forward to completing the building phase of Little Rock and moving on to the operational and deployment phases of each subsequent LCS. Our ability to operate for extended periods of time from forward operating stations will provide our Fleet commanders more flexibility and posture overseas."

COMLCSRON ONE and TWO support the operational commanders with warships ready for tasking by manning, training, equipping and maintaining littoral combat ships in the fleet.

Several additional Freedom-class LCSes are under construction at FMM in Marinette:

  • The future USS Sioux City (LCS 11) is preparing for trials later this fall.
  • The future USS Wichita (LCS 13) was christened and launched in September 2016 and is currently conducting system testing in the Menominee River, preparing for trials in the spring of 2018.
  • The future USS Billings (LCS 15) was christened and launched in July and is estimated to commence trials in the fall of 2018.
  • The future USS Indianapolis (LCS 17) is preparing for launch this winter, while the keel of the future USS St. Louis (LCS 19) was laid earlier this spring and is undergoing construction in FMM's erection bays.
  • The future USS Minneapolis St. Paul (LCS 21) started fabrication in February, while the future USS Cooperstown (LCS 23) started fabrication in September.
  • The future USS Marinette (LCS 25) is in the pre-production phase, having been awarded in 2016.

The FMM-Lockheed Martin team is currently in full-rate production and has delivered five ships to the Navy to date. There are currently seven ships in various stages of construction at FMM, with one more in long-lead production.

LCS is a modular, reconfigurable ship with three types of mission packages including surface warfare, mine countermeasures, and anti-submarine warfare. Program Executive Office for Littoral Combat Ships is responsible for delivering and sustaining littoral mission capabilities to the fleet. Delivering high-quality warfighting assets while balancing affordability and capability is key to supporting the nation's maritime strategy.

The LCS-class consists of the Freedom and Independence classes. The construction contract for the Freedom-class was awarded to FMM in 2010. The Independence team is led by Austal USA (for LCS 6 and follow-on even-numbered hulls). Twenty-seven LCS ships have been awarded to date: 11 have been delivered to the Navy, 13 are in various stages of construction, and three are in pre-production stages.