McDermott International announced today that one of its subsidiaries was awarded a contract to provide transportation and installation services to Walter Oil & Gas for the Megalodon platform destined for South Timbalier Block 311 in the Gulf of Mexico. The project is expected to be included in McDermott’s third quarter 2014 backlog.

McDermott will provide all materials and equipment to transport and install the six-pile platform in 391' of water over an existing well site. The heavy-lift Derrick Barge 50 will perform a side-lift of the 3,300-ton jacket and set the 2,100-ton topsides. Installation is expected to begin in the fourth quarter.  

“McDermott is pleased to work again for Walter to support its drilling and production activities,” said Dominic Savarino, vice president and general manager, McDermott Americas.