The U.S. Army Corps of Engineers’ Nashville District marked the completion of the upstream approach wall for the new Chickamauga Lock with a Nov. 16 ribbon cutting in Chattanooga, Tenn. The wall will guide commercial barges and recreational vessels into the replacement lock at Tennessee River mile 471.

The new 600’x100’ chamber will accommodate nine jumbo barges in a single lockage. The existing lock, which dates to 1940, can handle one jumbo barge at a time.

Prime contractor C.J. Mahan Construction Co. built the wall alongside an active hydroelectric dam. Crews drilled 14 shafts, each 8’ in diameter, through steel casings and into bedrock as deep as 135’ below the river surface. Ready-mix trucks staged on barges supplied thousands of cubic yards of concrete, which crews placed underwater using the tremie method to form the piers.

Two derrick crane barges worked in tandem to set eight precast concrete beams, each 120’ long and weighing 420 tons. Commercial divers guided the beams onto submerged bearing pads in turbulent currents before crews bolted the sections together. Four intermediate piers and two nose piers support the completed structure.

Crews logged more than 303,000 labor hours over 1,856 days without a lost-time injury, according to the Corps. Doug McCrae, managing partner of C.J. Mahan, said the company also completed the work on schedule and within budget.

“Accomplishing deep-water drilling, heavy tandem marine crane picks, and underwater diving directly adjacent to an active hydroelectric dam demanded exceptional skill,” McCrae said.

The Corps awarded C.J. Mahan the final approach wall and decommissioning contract in February 2026. Under that contract, crews will build the downstream approach walls, breach part of the existing dam to connect the upstream approach to the new chamber, and remove the temporary cofferdam. Commercial traffic will shift to the new lock as part of that work.